What is the total actual hours worked by Crew 1?

  1. 90

  2. 100

  3. 80

  4. 110

The correct answer is: 100

To find the total actual hours worked by Crew 1, it is important to consider how work hours are typically recorded and summed up. The total actual hours would include all shifts worked by each member of the crew. If Crew 1 worked multiple shifts or had varying hours of work across different days, you would add up those individual hours. It’s possible that Crew 1 had several members, each contributing to the total, or they might have worked a consistent schedule that needs to be calculated over a defined period. The key to arriving at the total of 100 hours likely hinges on accounting for every hour worked by each crew member. In a typical construction scenario or project timeline, the aggregate hours worked would also consider any overtime and regular work hours, which collectively may have led to the correct figure of 100. Thus, when assessing the data provided, finding the right combination of work hours, including potential overtime, leads to the accurate total of 100 hours.